This was done in accordance with the recommendation of the project owner, so as to accomplish works on time*
The rehabilitation works on the 36km road section Moutourwa-Maroua is executed by the groupement SOTCOCOG SA/STAPORT SA for an envelope of 21 135 523 591 CFAF all taxe included.
To date, the elevation and chaining works are completed on buildings aimed at accommodating (offices, housing, control mission). Let’s note that, the enterprise reported several contrains such as heavy rain fall as elements participating in delaying the advancement of the project. To fill this gap, and meet up with objectives fixed, the enterprise is
anticipating on the prefabrication of concrete massifs so as to accelerate works immediately after the rainy season.